Job Profile

Project : Monarch Stack 2005 Stack being fabricated in shop
Job Number : 15202
Client : Monarch Welding
Destination : SeverStal NA Foundry, Rouge Plant Dearborn, MI
Duration : 9 Weeks
Completion : 2005
Approx Value : $ .176 Million Stack being trucked to port
Approx Weight : 41 Ton
Ship Date : 2005
Ship Method : Barge shipped painted stack section complete
Project Description: "Expedited Project"
Fabricated lower round stack extension complete with anchor base ring, and (2) inlet flanges. Exhaust Stack Extension 17 foot diameter, and 45 foot tall of 3/8" and ½" HRS plate. Exterior shop painted. Unscheduled project expedited for installation during scheduled outage.

Finished stack was shipped along the High Wire Corridor.

Stack being trucked to port Stack being barged to Dearborn plant