Job Profile
| Project : | Monarch Stack 2005 |
|
| Job Number : | 15202 | |
| Client : | Monarch Welding | |
| Destination : | SeverStal NA Foundry, Rouge Plant Dearborn, MI | |
| Duration : | 9 Weeks | |
| Completion : | 2005 | |
| Approx Value : | $ .176 Million |
|
| Approx Weight : | 41 Ton | |
| Ship Date : | 2005 | |
| Ship Method : | Barge shipped painted stack section complete | |
| Project Description: | "Expedited Project" Fabricated lower round stack extension complete with anchor base ring, and (2) inlet flanges. Exhaust Stack Extension 17 foot diameter, and 45 foot tall of 3/8" and ½" HRS plate. Exterior shop painted. Unscheduled project expedited for installation during scheduled outage. Finished stack was shipped along the High Wire Corridor. |
|
|