Job Profile

Project : WGI Absorber Ductwork 2007 Large square to round ductwork sections for absorber ductwork project
Job Number : 16283
Client : Washington Group International
Destination : Monroe Power Plant Units No. 3 and No. 4, DTE, Monroe, MI
Duration : 36 weeks
Completion : 2008
Approx Value : $6.6 Million Absorber duct section
Approx Weight : 1,000 ton
Ship Date : Summer 2008
Ship Method : Barge Shipped, Insulated and Lagged Duct Modules direct to jobsite.
Project Description: Fabricated (2) Absorber Ductwork Systems in large modules to facilitate erection efficiency. Installed Free Issue Expansion Joint Frames, included fabrication of (2) ASME welded Quench Piping Systems, and Engineered Lifting Lug systems for erection. All Modules were shop Insulated and Lagged before being loade onto barge.

SCR ductwork on barge heading for jobsite SCR ductwork on barge heading for jobsite